Selecting an industrial steam turbine generator set involves more than choosing a power rating. The right configuration depends on available steam conditions, process steam demand, electrical load and annual operating hours.
For industrial projects, these factors determine not only the turbine type but also the generator capacity and auxiliary systems required.
1. Start with Available Steam Conditions
Steam conditions are the starting point for turbine selection. Key information includes:
- Inlet steam pressure and temperature
- Available steam flow
- Steam quality
- Required exhaust or back pressure
- Extraction pressure and flow, if applicable
The same steam flow can produce different power outputs under different operating conditions. Therefore, the turbine should be selected based on the actual steam balance rather than the target MW rating alone.
2. Compare Industrial Steam Turbine Types
Different turbine configurations serve different process and power requirements. The table below provides an initial comparison.
Turbine Type | Electricity Generation | Process Steam Supply | Condenser | Typical Applications |
Back-Pressure | ✓ | ✓ | Not normally required | CHP · Industrial process steam |
Condensing | ✓ | — | Required | Power generation · Waste heat recovery |
Extraction-Condensing | ✓ | ✓ | Required | CHP · Variable steam and power demand |
Extraction Back-Pressure | ✓ | ✓✓ | Not normally required | Multi-pressure process steam supply |
This table is for initial guidance. The final configuration depends on steam conditions, process demand and electrical requirements.
The required turbine capacity should match the plant's actual electricity demand and operating profile.
Consider:
- Normal, minimum and peak electrical loads
- Grid-connected or island operation
- Grid frequency: 50 Hz or 60 Hz
- Annual operating hours
- Load variations and planned shutdowns
- Whether surplus electricity will be exported
For projects with varying loads, annual power generation should be evaluated using the expected operating hours at each load level.
Annual net generation = Sum of (Net output × Operating hours at each load level)
This provides a more realistic basis for evaluating project benefits than rated power alone.
4. Match the Turbine with the Generator
The turbine and generator must be selected as a coordinated system.
Important considerations include:
- Turbine shaft power and generator rated output
- Generator capacity (kW/MW or kVA/MVA)
- Power factor
- Voltage and frequency
- Turbine and generator speed
- Number of poles
- Excitation and cooling systems
- Synchronization and electrical protection
Direct coupling or a reduction gearbox may be selected according to the turbine speed and generator requirements.
5. Configure the Auxiliary Systems
A complete turbine generator set requires more than the main turbine and generator. Auxiliary equipment must be matched to the selected configuration.
System | Main Function |
Lubricating oil system | Supplies oil to bearings and related components |
Gland sealing system | Controls steam leakage and air ingress |
Condenser and vacuum system | Condenses exhaust steam in condensing configurations |
Cooling system | Removes heat from the condenser and auxiliary equipment |
DEH / ETS / TSI / DCS | Governing, emergency protection, condition monitoring and system coordination |
Electrical system | Excitation, synchronization, switchgear and protection |
The actual auxiliary scope depends on the turbine type, operating conditions and project requirements.
6. Understand Rated Power and Net Electrical Output
When comparing turbine generator sets, it is important to distinguish between three power values:
Turbine rated power: Mechanical power delivered at the turbine shaft under specified design conditions.
Generator gross output: Electrical power measured at the generator terminals.
Net electrical output: Power available to the plant after deducting the agreed auxiliary consumption.
For example, if a generator produces 10 MW at its terminals and the relevant auxiliary systems consume 0.3 MW:
Net electrical output = 10 MW − 0.3 MW = 9.7 MW
The measurement boundary should be clearly defined when comparing technical proposals or evaluating performance guarantees.
7. Define the Project Supply Scope
Before finalizing a technical proposal, clarify the equipment and services included in the package.
Typical scope may include:
- Steam turbine and generator
- Coupling or reduction gearbox
- Lubricating oil and governing systems
- Emergency trip and monitoring systems
- Condenser and vacuum equipment, where required
- Electrical control and protection equipment
- Instrumentation and specified auxiliary equipment
Also clarify responsibilities for external steam piping, cooling towers, transformers, civil works, installation, commissioning and other site services.
8. What Information Is Needed for Preliminary Selection?
To evaluate a suitable 1–60 MW turbine generator set, the following information is helpful:
Information | Key data required |
Process requirements | Required steam pressure, flow and temperature |
Power demand | Normal, minimum and peak electrical loads |
Operating profile | Annual operating hours and load variations |
Turbine arrangement | Back-pressure, extraction or condensing preference, if known |
Electrical system | Voltage, frequency, power factor and grid connection |
Cooling conditions | Cooling water temperature, availability and site conditions |
Project scope | Turbine-generator set or complete turbine-island package |
YTS Industrial Steam Turbine Generator Solutions
YTS supplies industrial steam turbines and generator sets from 1 MW to 60 MW, including back-pressure, condensing, extraction-condensing and extraction back-pressure configurations.
Our engineering team can provide preliminary turbine selection and technical support based on your steam parameters, process requirements and electrical demand.
Have a project under development? Share your available steam conditions and power requirements with YTS for an initial technical evaluation.