YTS 20 MW Back-Pressure Steam Turbine Upgrade Project Successfully Passes Performance Acceptance Testing

Created on 07.17
YTS has successfully completed the performance acceptance of a 20 MW back-pressure steam turbine generator retrofit project for Sanmenxia Aluminum Co., Ltd. The project represents another important milestone in YTS’s delivery of energy-efficiency upgrades and turnkey steam turbine solutions.
Project at a Glance
Project type
Turnkey energy-efficiency retrofit and capacity upgrade
Original installed capacity
12 MW
New installed capacity
20 MW steam turbine + 20 MW generator
Turbine model
B20-8.83/1.08//535
Design feature
High-efficiency, multistage pressure-stage configuration with a 10% overload margin
Acceptance result
Specific steam consumption: 7.481 kg/kWh
Project Background
The original back-pressure turbine generator set had an installed capacity of 12 MW. As the customer expanded production, additional power capacity was required. At the same time, the existing unit was operating with low internal efficiency and high specific steam consumption, resulting in significant energy losses.
To address both capacity and efficiency requirements, the project called for replacing the original unit with a new 20 MW high-efficiency steam turbine generator set. The upgrade was designed not only to increase output, but also to reduce steam consumption and improve overall energy utilization.
0
YTS Turnkey Solution
To address these challenges, YTS supplied a new high-efficiency 20 MW back-pressure steam turbine generator set to replace the original unit. The upgrade was designed to achieve two key objectives: increasing power generation capacity and improving overall steam utilization efficiency.
The new steam turbine, model B20-8.83/1.08/535, adopts a highly efficient multi-stage configuration. Both the steam turbine and generator are rated at 20 MW, with a 10% overload capability.
To optimize the customer’s investment, YTS also reused and upgraded parts of the existing turbine island. The project scope included:
  • Engineering and supply of the new turbine generator set
  • Reinforcement and modification of the existing foundation
  • Upgrading and reuse of suitable turbine-island facilities
  • Integration of selected auxiliary equipment
  • Installation, commissioning and performance testing
Performance Acceptance Results
During the final performance assessment, the unit achieved a specific steam consumption of 7.481 kg/kWh, meeting the agreed technical requirements and delivering the expected energy-efficiency benefits.
YTS completed all contractual responsibilities—from equipment manufacturing and delivery to foundation reinforcement, installation and commissioning—in accordance with the project schedule and technical standards. The overall execution and final performance were highly recognized by the customer.
The successful completion of this project adds another benchmark reference to YTS’s turnkey project portfolio and strengthens the company’s position in the industrial energy market in Henan Province.
0
YTS welcomes industrial enterprises and project partners to visit the project site and exchange ideas on steam turbine capacity upgrades, energy-efficiency retrofits and industrial power generation solutions.
Together, we can improve energy efficiency, reduce carbon emissions and create long-term value through reliable industrial steam turbine technology.